Final Inspection of 10 SCB18 Transformers Before Shipment: Jiangsu Unita Electric Equipment Supports Beijing Wanji (Gaotai) Intelligent Computing Center

Time : 2026-10-09

Jiangsu Unita Electric Equipment Co.,Ltd. has completed the pre-shipment final inspection of 10 SCB18 dry-type transformers. The units will be shipped to Gaotai County, Zhangye City, Gansu Province, for the Beijing Wanji (Gaotai) Intelligent Computing Center project.

Project Background

The Beijing Wanji (Gaotai) Intelligent Computing Center is located in Nanhua Industrial Park, Gaotai County. It is a key provincial project in Gansu Province, invested and built by Beijing Wanji Data Technology Co., Ltd. The project has a total investment of 1.46 billion yuan and plans to build nearly 20,000 square meters of intelligent computing center buildings with 500 standard racks.

After completion, the project will reach a half-precision theoretical peak computing power of no less than 5000 PFlops. It will focus on green low-carbon data centers, cloud computing, and industry AI solutions. Once fully built, the center is expected to consume 2.101 billion kWh of electricity annually, placing high demands on the energy efficiency and reliability of power distribution equipment.

Transformer Selection

The 10 transformers shipped this time have the following capacity configuration: 6 units of 1600kVA, 2 units of 1250kVA, and 2 units of 2000kVA. The 1600kVA and 1250kVA units cover general power distribution, while the 2000kVA units handle core power supply for high-power racks.

The SCB18 is a Grade 1 energy efficiency dry-type transformer under the current national standard GB 20052. Jiangsu Unita Electrical Equipment selected the configuration based on the project’s load rate and annual operating hours. The intelligent computing center operates 24 hours a day with a consistently high load rate, so the low-loss characteristics of the SCB18 can reduce long-term operating electricity costs. The oil-free design of the dry-type transformer eliminates explosion risks and allows direct deployment in indoor distribution rooms.

Capacity (kVA)

Quantity

Application Scenario

1600

6 units

General power distribution

1250

2 units

General power distribution

2000

2 units

Core power supply for high-power racks

Total

10 units

Main computer room power distribution

Table 1. Capacity configuration of the 10 SCB18 transformers

Pre-Shipment Final Inspection

Four-point inspection protocol

1. Winding and cast resin inspection Each unit was checked for bubbles or mechanical damage in the epoxy resin cast body to rule out insulation hazards.

2. Energy efficiency testing Each transformer completed energy efficiency testing with a test report issued. No-load loss and load loss data were reviewed unit by unit to ensure compliance with Grade 1 energy efficiency standards.

3. Temperature control and protection system testing The SCB18 comes standard with F-class insulation, winding temperature controllers, and fans. Power-on tests verified temperature controller logic, fan activation thresholds, and communication interface functions.

4. Document and nameplate verification The serial number, factory test report, certificate of conformity, and installation manual of each unit were matched one by one. Information files for all 10 units are traceable.

微信图片_20261009112808_603_5.jpg

About Jiangsu Unita Electric Equipment Co.,Ltd.

Jiangsu Unita Electric Equipment Co.,Ltd. is a winning bidder for State Grid and China Southern Power Grid. We produce high and low voltage complete equipment, box-type substations, and dry-type and oil-immersed transformers, with an annual delivery capacity of 15,000 units.

In energy efficiency customization, Unita Electric Equipment matches models to project scenarios: SCB18 Grade 1 energy efficiency units for high-standard scenarios such as data centers and hospitals, and Grade 2 energy efficiency solutions for general scenarios. The company’s equipment has recorded over 1,000 days of zero-failure operation in photovoltaic power stations and charging pile clusters.

Conclusion

After final inspection, the 10 SCB18 transformers will be shipped to the Gaotai Intelligent Computing Center construction site for the main computer room power distribution system. Jiangsu Unita Electrical Equipment Co.,Ltd. provides power distribution equipment support for this project.